Oracle Primavera Procedures
Use these procedures when working with Oracle Primavera.
Related Topics:
- Import a Primavera P6 File Through Web Services
Use these steps to link to and import a Primavera P6 file through web services. - Set the Oracle Primavera Platform Options
Specify whether you want to calculate baseline values from planned or current values and set the number of seconds before the web service times out. - Assign a P6 Baseline to a P6 Schedule
Assign a P6 baseline to a P6 schedule. Assigning a P6 baseline to a P6 schedule allows you to compare baseline data with the current schedule. - Remove a P6 baseline from a P6 Schedule
Use these steps to remove an existing P6 baseline from a P6 schedule. - Select a Different P6 Baseline
Select a different P6 baseline for a P6 schedule that already has a baseline assigned. - Assign a Primavera file as Both a Snapshot and Baseline
Assign a Primavera file as both a snapshot and a baseline at the same time. A snapshot allows comparisons between versions of a single project. Assigning a P6 baseline to a P6 schedule allows you to compare baseline data with the current schedule. - Select Text Encoding for Oracle Primavera Imports
XER files do not include any information about what is being used to encode the files. If the file you are importing does not use standard encoding (for example, it uses Russian instead of English), then the characters may not display correctly when you import the file.
Parent Topic: External Data Sources Procedures